You have a project with four activities as follows. Activity 1 can start immediately and has an estimated duration of 1. Activity 2 can start after activity 1 is completed and has an estimated duration of 4. Activity 3 can start after activity 2 is completed and has an estimated duration of 5. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and activity 4 must be completed before the project is complete. What is the critical path of the project?
A. Start, 1, 2, 3, End
B. Start, 1, 4, 3, End
C. Start, 1, 4, End
D. Start, 1, 2, 3, 4, End

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 01:00
What is added to the < meta > tag to describe the encoding type?
Answers: 2
question
Computers and Technology, 22.06.2019 09:40
In the lab, which of the following displayed a list of all installed services and included a description of the service, the current state, and whether the service started automatically or manually? a. the services manager b. the applications summary c. the recommended services d. list the safe services list
Answers: 2
question
Computers and Technology, 22.06.2019 23:00
In which part of a professional email should you try to be brief, but highly descriptive?
Answers: 1
question
Computers and Technology, 23.06.2019 02:00
Which of the following is not a source of sustainable raw materials? a) coal mine b) flick of sheep c) cotton plantation d) line forest.
Answers: 2
You know the right answer?
You have a project with four activities as follows. Activity 1 can start immediately and has an esti...
Questions
question
Mathematics, 18.03.2021 21:50
Questions on the website: 13722360