Computers and Technology, 18.10.2020 14:01 dezmondpowell
A project consists of 8 activities. The activity completion times and the precedence relationships are as follows:
Activity. Completion time Days. immediate predecessor activities.
A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F
1. Draw the network diagram using AON model notations:
2. What is the critical path?
3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.
4. What is the minimum time to complete the projects?
Please answer and thank you
Answers: 1
Computers and Technology, 22.06.2019 06:50
Match the personality traits with their description
Answers: 1
Computers and Technology, 23.06.2019 05:20
What did creator markus “notch" persson initially call his game
Answers: 1
Computers and Technology, 23.06.2019 18:30
Janice recently received her college degree and is looking for a job. she is worried that since she just finished school, she will be required to repay her perkins and direct subsidized loans immediately. janice pulls out the paperwork she signed and reviews it again for repayment information. after reading all of the information, janice discovers that
Answers: 2
Computers and Technology, 24.06.2019 09:40
Healthy study habits are best described as
Answers: 1
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Physics, 06.06.2021 18:40
English, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
History, 06.06.2021 18:40
Computers and Technology, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
English, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
Chemistry, 06.06.2021 18:40
Mathematics, 06.06.2021 18:40
Computers and Technology, 06.06.2021 18:40