A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 04:31
Type the correct answer in the box. spell all words correctly. the managing director of a company sends a christmas greeting to all his employees through the company email. which type of network does he use? he uses an
Answers: 1
question
Computers and Technology, 23.06.2019 07:30
Which option allows you to view slides on the full computer screen?
Answers: 1
question
Computers and Technology, 23.06.2019 08:30
Helen's credit card has an apr of 15.32% and a grace period of 17 days and helen pays her balance in the full every month. if her last billing cycle ended on september 26, 2009, and she made her payment on october 11, 2009, did she owe any interest on her last statement's balance?
Answers: 3
question
Computers and Technology, 23.06.2019 18:00
Ramona enjoys her job because she is able to kids in an after school program. the work value ramona feels strongest about is a. leadership b. risk c. independence d. work with people select the best answer from the choices provided a b c d
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Health, 14.10.2019 23:40
question
Social Studies, 14.10.2019 23:50
Questions on the website: 13722367