A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 05:00
This program will store roster and rating information for a soccer team. coaches rate players during tryouts to ensure a balanced team. (1) prompt the user to input five pairs of numbers: a player's jersey number (0 - 99) and the player's rating (1 - 9). store the jersey numbers in one int vector and the ratings in another int vector. output these vectors (i.e., output the roster). (3 pts) ex: enter player 1's jersey number: 84 enter player 1's rating: 7 enter player 2's jersey number: 23 enter player 2's rating: 4 enter player 3's jersey number: 4 enter player 3's rating: 5 enter player 4's jersey number: 30 enter player 4's rating: 2
Answers: 1
question
Computers and Technology, 22.06.2019 10:30
You are almost finished updating a web site. as part of the update, you have converted all pages from html 4.0 to html5. the project is currently on schedule. however, your project manager has been asked by the marketing team manager to justify a day of time spent validating the site's html5 pages. the marketing team manager does not have technical knowledge of the internet or the web. which is the most appropriate explanation to provide to the marketing team manager?
Answers: 1
question
Computers and Technology, 22.06.2019 22:00
What is the name of the option in most presentation applications with which you can modify slide elements? 1. the option enables you to modify a slide element in most presentation applications.
Answers: 3
question
Computers and Technology, 23.06.2019 07:50
Apython programming question: assume s is a string of lower case characters. write a program that prints the number of times the string 'bob' occurs in s. for example, if s = 'azcbobobegghakl', then your program should print number of times bob occurs is: 2
Answers: 3
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 02.11.2020 04:50
question
Mathematics, 02.11.2020 04:50
question
Mathematics, 02.11.2020 04:50
question
Computers and Technology, 02.11.2020 04:50
question
History, 02.11.2020 05:00
question
Health, 02.11.2020 05:00
Questions on the website: 13722360