You have a project with the following tasks: Task A takes 40 hours and can start after the project starts. Task B takes 25 hours and should happen after the project starts. Task C must happen after Task A and takes 35 hours. Task D must happen after Tasks B and C and takes 30 hours. Task E must take place after Task C and takes 10 hours. Task F takes place after Task E and takes 22 hours. a. Draw the network diagram
b. What is the critical path and what is the length of the critical path?
c. If Task B actually takes 37 hours, what is the effect on the project?
d. What tasks must be completed before task D can begin?
e. If senior management tells you to complete the project 20 hours early, what is the project float? How can you meet this requirement? Does the critical path change?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 18:00
What ordering of tcp flags makes up the three-way handshake?
Answers: 2
question
Computers and Technology, 22.06.2019 04:30
How can you know if the person or organization providing the information has the credentials and knowledge to speak on this topic? one clue is the type of web site it is--the domain name ".org" tells you that this site is run by a nonprofit organization.
Answers: 2
question
Computers and Technology, 22.06.2019 22:50
Assume the existence of a bankaccount class. define a derived class, savingsaccount that contains two instance variables: the first a double, named interestrate, and the second an integer named interesttype. the value of the interesttype variable can be 1 for simple interest and 2 for compound interest. there is also a constructor that accepts two parameters: a double that is used to initialize the interestrate variable, and a string that you may assume will contain either "simple", or "compound", and which should be used to initialize the interesttype variable appropriately. there should also be a pair of functions getinterestrate and getinteresttype that return the values of the corresponding data members (as double and int respectively).
Answers: 2
question
Computers and Technology, 23.06.2019 01:30
How do you set up a slide show to play continuously, advancing through all the slides without requiring your interaction? a. click set up slide show, and then select the loop continuously until ‘esc' and show without narration options. b. click set up slide show, and then select the loop continuously until ‘esc' and use timings, if present options. c. click set up slide show, and then select the show presenter view and use timings, if present options. d. click set up slide show, and then select the show without animation and browsed at a kiosk (full screen) options.
Answers: 3
You know the right answer?
You have a project with the following tasks: Task A takes 40 hours and can start after the project s...
Questions
question
Mathematics, 17.01.2020 04:31
question
Mathematics, 17.01.2020 04:31
question
Mathematics, 17.01.2020 04:31
question
Mathematics, 17.01.2020 04:31
question
Mathematics, 17.01.2020 04:31
question
Mathematics, 17.01.2020 04:31
Questions on the website: 13722361