At krispy kreme the process for sugar coating donuts by the sugar-waterfall donut coater involves a flow of uncoated donuts into the donut coater and the output consists of the sugar coated donuts. the coater also receives an inflow of sugar suspension which coats the donuts. the unused sugar suspension is recycled to a mixer which is positioned ahead of the donut coater. an input pipe goes into the mixer and supplies sugar suspension which replaces the sugar that coats the donuts and leaves the system. the flow rate of donuts into the coater is 1200 donuts/hr and each uncoated donut weights approximately 110 g. 12 kg/h of sucrose suspension leaves the system when the donuts are coated but most of the sugar is recycled through the mixer. the mixer output stream of sucrose suspension has a mass flow rate of 126 kg/hr.

a. create a process flow diagram of the donut coater system described above, labeling the input mass flow of sugar suspension as m1 and the output flow of coated donuts as m2, and the recycle flow as m3. label the output mass fractions of donuts and sugar suspension using as few variables as possible. (5 points)
b. what is the mass flow of coated donuts? (5 points)
c. what is the mass flow of input sugar suspension (5 points)
d. what is the mass flow of the recycled sugar suspension (5 points)
e. what is the mass fraction of sugar suspension on the coated donuts? (5 points)

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
question
Engineering, 04.07.2019 18:10
Water at the rate of 1 kg/s is forced through a tube with a 2.5 cm inner diameter. the inlet water temperature is 15Β°c, and the outlet water temperature is 50Β°c. the tube wall temperature is 14Β°c higher than the local water temperature all along the length of the tube. what is the length of the tube?
Answers: 3
question
Engineering, 04.07.2019 19:10
In general, how do thermosetting plastics compare to thermoplastics in mechanical and physical properties?
Answers: 3
You know the right answer?
At krispy kreme the process for sugar coating donuts by the sugar-waterfall donut coater involves a...
Questions
question
Mathematics, 13.02.2023 01:10
question
Mathematics, 13.02.2023 04:40
Questions on the website: 13722359