Engineering, 14.02.2020 04:09 noahdavis58

During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective) parts and 17 defective parts were produced. The operation cycle consists of a processing time of 5.23 min, and a part handling time of 0.58 min. Every 50 parts, a tool change is performed, and this takes 4.2 min. The machine experienced several breakdowns during the week.
Determine
(a) hourly production rate of acceptable parts,
(b) scrap rate, and
(c) availability (proportion uptime) of the machine during this week.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The higher the astm grain size number, the finer the gran is. a)-true b)-false
Answers: 2
question
Engineering, 04.07.2019 18:20
Aheavily insulated piston-cylinder device contains 0.02 m3 of steam at 300 kpa and 200 °c. 1.2 mpa. d this process. team is now compressed in a reversible manner to a pressure of etermine the entropy change and the work done on the steam during this process
Answers: 1
question
Engineering, 04.07.2019 19:10
Abarometer contains mercury with a density of 13600 kg/m3. atmospheric conditions are 95.8 kpa and 20 °c at 20 °c, the vapor pressure of the mercury is 0.000173 kpa. the column of mercury will rise to a height of most nearly. select one: a)- 0.38 m b)- 0.82 m c)- 0.48 m d)- 0.72 m
Answers: 1
question
Engineering, 05.07.2019 04:30
Technician a says that in a worm gear steering system, most excessive steering free play is usually found in the gearbox. technician b says that in a rack-and-pinion steering system, excessive free play can be found in the bushings. who is correct?
Answers: 2
You know the right answer?
During a particular 40-hour week of an automated production operation, 381 acceptable (nondefective)...
Questions
question
Mathematics, 10.12.2020 17:50
question
Mathematics, 10.12.2020 17:50
question
German, 10.12.2020 17:50
question
Mathematics, 10.12.2020 17:50
Questions on the website: 13722361