Engineering, 18.02.2020 05:28 scully1442

How many hours should it take an articulated wheel loader equipped with a 4-yd^3 bucket to load 3000 yd^3 of gravel (average material)from a stockpile into rail cars if the average haul distance is 300 ft one way? The area is level with a rolling resistance factor of 120 lb/ton. Job efficiency is estimated at 50 min/h.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 23:20
Two technicians are discussing the intake air temperature (iat) sensor. technician a says that the computer uses the iat sensor as a backup to the engine coolant temperature (ect) sensor. technician b says that the powertrain control module (pcm) will subtract the calculated amount of fuel if the air measures hot. who is correct
Answers: 3
question
Engineering, 04.07.2019 16:10
An electrical motor raises a 50kg load at a construct velencity .calculate the power of the motor, if it takes 40sec to raise the load through a height of 24m(take g =9.8n/g)
Answers: 2
question
Engineering, 04.07.2019 18:10
The drive force for diffusion is 7 fick's first law can be used to solve the non-steady state diffusion. a)-true b)-false
Answers: 1
question
Engineering, 04.07.2019 18:10
Which of the following ziegler nichols tuning methods the response of the controller to a step input should exhibit an s-shaped curve? a)-open loop mode b)-closed loop mode c)-both modes (open & closed) d)-none of the modes (open & closed)
Answers: 3
You know the right answer?
How many hours should it take an articulated wheel loader equipped with a 4-yd^3 bucket to load 3000...
Questions
question
History, 21.05.2020 02:05
question
Mathematics, 21.05.2020 02:05
question
History, 21.05.2020 02:05
question
SAT, 21.05.2020 02:05
question
Chemistry, 21.05.2020 02:05
Questions on the website: 13722360