There are 10 vehicles in a queue when an attendant opens a toll booth. Vehicles arrive at the booth at a rate of 4 per minute. The attendant opens the booth and improves the service rate over time following the function u(t) = 1.1 + .30t, where u(t) is in vehicles per minute and t is in minutes. I need to find the maximum queue length. I included my solution below for the total delay.

u(t) = 4 when t = (4-1.1)/0.3 = 9.67mins
(9.67 to t) ? (1.1+0.3t)dt = 10
? 1.1t + 0.15t2 ](9.67 to t)= 10
? t = 11.97mins
So, delay = 11.97 – 9.67 = 2.30mins

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 16:10
An electrical motor raises a 50kg load at a construct velencity .calculate the power of the motor, if it takes 40sec to raise the load through a height of 24m(take g =9.8n/g)
Answers: 2
question
Engineering, 04.07.2019 18:10
Items are similar to the free issue items, but their access is limited. (clo5) a)-bin stock items free issue b)-bin stock controlled issue c)-critical or insurance spares d)-rebuildable spares e)-consumables
Answers: 1
question
Engineering, 04.07.2019 18:10
Calculate the bore of a cylinder that has a stroke of 18 inches and an extension time of 6 seconds at a flow rate of 4 gal/min.
Answers: 3
question
Engineering, 04.07.2019 18:20
Air is compressed isentropically from an initial state of 300 k and 101 kpa to a final temperature of 1000 k. determine the final pressure using the following approaches: (a) approximate analysis (using properties at the average temperature) (b) exact analysis
Answers: 1
You know the right answer?
There are 10 vehicles in a queue when an attendant opens a toll booth. Vehicles arrive at the booth...
Questions
question
Mathematics, 03.08.2019 08:50
question
Health, 03.08.2019 08:50
question
Health, 03.08.2019 08:50
Questions on the website: 13722360