Engineering, 27.02.2020 21:42 19deleonl

A heat recovery system (HRS) is used to conserve heat from the surroundings and supply it to the Mars Rover. The HRS fluid loops use Freon as the working fluid. The instrumentation must be kept as a temperature greater than −67 degrees Fahrenheit [°F] to avoid damage.

The temperature in the area of Mars where the rover is exploring is 189 kelvins [K]. If the system must remove 47.4
British Thermal Units [BTU] of energy, what volume of Freon is needed in units of liters [L]?

Some facts about Freon:
The specific heat of Freon is 74
joules per mole kelvin J/(mol °K)]
The specific gravity of Freon is 1.49
The molecular mass of Freon is 120 grams per mole [g/mol]

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 19:30
When using the ohmmeter function of a digital multimeter, the leads are placed in what position relative to the component being tested? a. parallel b. control c. series d. line
Answers: 3
question
Engineering, 04.07.2019 18:10
Aloaded platform of total mass 500 kg is supported by a dashpot and by a set of springs of effective stiffness 72 kn/m. it is observed that when the platform is depressed through a distance x = 12.5 cm below its equilibrium position and then released without any initial velocity; it reaches its equilibrium position in the shortest possible time without overshoot. find the position and velocity of the loaded platform 0.10 sec. after its release. if a further load of 400 kg is added to the platform, find, i) the frequency of damped vibrations, and i) the amplitude of vibration after 2 complete oscillations, given that the initial amplitude is 15 cm.
Answers: 1
question
Engineering, 04.07.2019 18:10
Different types of steels contain different elements that alter the characteristics of the steel. for each of the following elements, explain what the element does when alloyed with steel.
Answers: 2
question
Engineering, 04.07.2019 19:10
An external consultant recommends that a plant installs a bank of capacitors for power factor correction. this will reduce the peak electrical demand charges by an average of 93 kw every month. the plant current pays $13 per kw in peak demand charges. the capacitor bank will include 223 kw of fixed capacitors, and 183 of variable capacitors. the fixed capacitors cost $59 per kw, and the variable capacitors will cost $65 per kw. the consultant charges 21% of the equipment costs to install the capacitors. because this project will reduce the demand for the electric utility, they are prepared to provide a one-time rebate of $42 per kw of reduced demand. what is the simple payback period for this project (in years)?
Answers: 2
You know the right answer?
A heat recovery system (HRS) is used to conserve heat from the surroundings and supply it to the Mar...
Questions
question
Mathematics, 13.01.2020 19:31
question
Mathematics, 13.01.2020 19:31
Questions on the website: 13722367