An excavator ($300/hour) with a 4 cubic yard bucket loads trucks ($200/hour each).Trucks carry 18 cubic yards. Each cycle of the excavator is 30 seconds (4 yd3 each 30

seconds). We can either load the truck full (18 yd3) in 5 cycles or partially full (16 yd3) in 4 cycles. Assume 100% productive (60 minutes/60 minutes)In either case, the truck takes 6.5 minutes to travel, dump and return.

a. Option 1: 5 cycles of the excavator, 18 yd3 in the truck.

i. Determine the number of trucks to balance the operation, to 1 decimal place

ii. Round the number of trucks up, determine the productivity in yd3/hour

iii. Determine the cost per hour (round to nearest dollar) and cost per cubic yard(round to nearest cent/yd3) to load and haul the soil.

b Option 2: 4 cycles of the excavator, 16 yd3 in the truck.

i. Determine the number of trucks to balance the operation, to 2 decimal places

ii. Round the number of trucks up, determine the productivity in yd3/hour

iii. Determine the cost per hour and cost per cubic yard to load and haul the soil

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Ahouse has the following electrical appliance usage (1) single 40w lamp used for 4 hours per day (2) single 60w fan used for 12 hours per day (3) single 200w refrigerator that runs 24 hours per day with compressor run 12 hours and off 12 hours find the solar power inverter size in watt with correction factor of 1.25.
Answers: 1
question
Engineering, 04.07.2019 18:10
Items are similar to the free issue items, but their access is limited. (clo5) a)-bin stock items free issue b)-bin stock controlled issue c)-critical or insurance spares d)-rebuildable spares e)-consumables
Answers: 1
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
question
Engineering, 04.07.2019 18:20
How much power could a wind turbine produce if it had the following specifications? cp = 0.45 -d=1.2kg/m3 d=50m v 5m/s
Answers: 2
You know the right answer?
(Construction Management Fundamental) Civ / Arch E

An excavator ($300/hour) with a 4 cub...
Questions
question
Mathematics, 13.02.2021 14:00
question
Biology, 13.02.2021 14:00
question
Arts, 13.02.2021 14:00
question
Mathematics, 13.02.2021 14:00
question
Mathematics, 13.02.2021 14:00
question
Mathematics, 13.02.2021 14:00
Questions on the website: 13722361