subject
Engineering, 19.05.2020 05:57 luvberries2276

1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update schedule indicates that a delay of 9 days has been experienced in the execution of Activity B and that a delay to the start of Activity D has consumed this activity’s “free float”. Clearly provide answers (numeric figures accompanied by clear explanations regarding the basis of the numeric figures) to the following:

a) What is the “now” projected total project duration and what drives this new figure

b) Explain the change (if any) to the total float of Activity L?

c) How much free and total floats can still be enjoyed by Activity D?

d) Given the delays described above, and provided that Activities C and F are shown to have been completed but with a joint consumption of 4 out of the 7 days of total float that were originally available to the C-F-K activity chain: (i) what interference (in days) to the scheduling of Activity K can be solely attributed to the completed execution of Activity B? (3 points) And, (ii) what total float can still be enjoyed by Activity K?

2- Given the delay reported to have taken place to the start of Activity D and the flexibility (if any) being now enjoyed (currently under the updated schedule), please argue what circumstances would warrant that the contractor’s PM, in consultation with his site-management subordinates, considers adopting a revised method of work, crew assignment (no. of crews), and/or work-shift schedule, and whether any one or more of these circumstances is/are evident in the updated schedule in connection with the scheduling results newly computed for D.

3- Assume the total duration for the project under study is expressed in months, totaling 14 months, on the basis of adopting a DBB project delivery approach. When will an estimate of this overall duration have been first made? And, what kind of control will be needed regarding this 14-month duration if the owner decides to switch to the “CM at Fee” approach at the point of time when the design phase has reached around 30% completion?

ansver
Answers: 2

Another question on Engineering

question
Engineering, 03.07.2019 14:10
Explain the difference laminar and turbulent flow. explain it with the shear stress and the velocity profiles.
Answers: 1
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
question
Engineering, 04.07.2019 18:10
True or false (explain) (110)[111] is a slip system in bcc metals . the {111} family in fcc contains 8 planes. resolved shear stress (rss) in single crystals is just related to the applied stress. critical resolved shear stress (crss) in single crystal metals is direct proportional to the number of defects in the structure
Answers: 2
question
Engineering, 04.07.2019 18:10
Aturning operation is performed with following conditions: rake angle of 12°, a feed of 0.35 mm/rev, and a depth of cut of 1.1 mm. the work piece is aluminum alloy 6061 with t6 heat treatment (a16061-t6). the resultant chip thickness was measured to be 1.0 mm. estimate the cutting force, fc. use shear stress of 207 mpa and coefficient of friction on the tool face of 0.6.
Answers: 1
You know the right answer?
1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update...
Questions
question
Business, 10.10.2019 19:00
question
History, 10.10.2019 19:00
question
Mathematics, 10.10.2019 19:00
Questions on the website: 13722359