(a) Three borrow pits are available for a highway embankment project. Explain the procedure for the selection of the proper borrow pit. How do you use compaction communicate with the contractor? How do you make sure that the contractor work meeting your specifications? (b) The results of a standard Proctor test are given below. Determine the maximum dr weight of compaction and the optimum moisture content.
(c) For the soil, if G-2.72, determine the void ratio and the degree of saturation at op moisture content.
Volume of Weight of Moisture content
Proctor mold( ft3) wet soil in the mold (lb) %
1/30 3.26 8.4
1/30 4.15 10.2
1/30 4.67 12.3
1/30 4.02 14.6
1/30 3.63 16.8

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Ahouse has the following electrical appliance usage (1) single 40w lamp used for 4 hours per day (2) single 60w fan used for 12 hours per day (3) single 200w refrigerator that runs 24 hours per day with compressor run 12 hours and off 12 hours find the solar power inverter size in watt with correction factor of 1.25.
Answers: 1
question
Engineering, 04.07.2019 18:10
Acompressor receives the shaft work to decrease the pressure of the fluid. a)- true b)- false
Answers: 3
question
Engineering, 04.07.2019 18:10
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
question
Engineering, 04.07.2019 18:10
Which of the following controllers anticipates the future from the slope of errors over time? a)-proportional b)-on/off c)-integral d)-derivative.
Answers: 2
You know the right answer?
(a) Three borrow pits are available for a highway embankment project. Explain the procedure for the...
Questions
Questions on the website: 13722360