subject
Engineering, 19.02.2021 03:00 weeman7760

There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for a truck to drive to the unloading site, unload and drive back to the excavation area. Instead of being idle till the trucks return from each truck cycle, the excavator unloads soil in a spoil bank at the same swing angle (90o). Calculate the volume of soil in the spoil bank at the end of the excavation. Total volume of excavation is 15,000 BCY.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Fluids at rest possess no flow energy. a)- true b)- false
Answers: 3
question
Engineering, 04.07.2019 18:10
Coiled springs ought to be very strong and stiff. si3n4 is a strong, stiff material. would you select this material for a spring? explain.
Answers: 2
question
Engineering, 04.07.2019 18:10
Water in a partially filled large tank is to be supplied to the roof top, which is 8 m above the water level in the tank, through a 2.2-cm-internal-diameter pipe by maintaining a constant air pressure of 300 kpa (gage) in the tank. if the head loss in the piping is 2 m of water, determine the discharge rate of the supply of water to the roof top in liters per second.
Answers: 3
question
Engineering, 04.07.2019 18:10
Courses that are developed by subject matter experts, internal or extemal to the college or university. these programs are marketed by the school (clo2) marks a)-vocational schools b)-vendor training c)-colleges & universities d)-continuing education programs
Answers: 2
You know the right answer?
There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for...
Questions
question
Mathematics, 20.07.2019 01:00
Questions on the website: 13722361