Engineering, 10.07.2021 18:40 pattydixon6

C. Assuming a fixed-priority scheduling. Consider two tasks to be executed periodically on a single processor, where task 1 has period p= 4 and task 2 has period p= 6. If execution time of task I be e;=1
Find the maximum value for the execution time e2 of task 2 such that the Rate Monotonic (RM) schedule is feasible. ​

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Aplate clutch has a single pair of mating friction surfaces 250-mm od by 175-mm id. the mean value of the coefficient of friction is 0.30, and the actuating force is 4 kn. a) find the maximum pressure and the torque capacity using the uniform-wear model. b) find the maximum pressure and the torque capacity using the uniform-pressure model.
Answers: 3
question
Engineering, 04.07.2019 18:10
The filament of an incandescent lamp has a temperature of 2000k. calculate the fraction of radiation emitted in the visible light band if the filament is approximated as blackbody
Answers: 2
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
question
Engineering, 04.07.2019 18:20
What is the heat treatment of metals? what is the benefit of it? why and how it's useful? answer in details, do not write by hand.
Answers: 3
You know the right answer?
C. Assuming a fixed-priority scheduling. Consider two tasks to be executed periodically on a single...
Questions
question
Mathematics, 12.04.2021 17:40
question
Social Studies, 12.04.2021 17:40
question
Biology, 12.04.2021 17:40
Questions on the website: 13722359