An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a budget of $8,000. During a performance review, which took place 7 weeks after the activity was initiated, it was found that 50% of the work had already been completed and that the actual cost was $4,500. a) Calculate the EV of the activity.
b) Calculate the cost performance index (CPI) and schedule performance index (SPI).
c) Calculate the expected Budget at Complete (BAC) using the initial estimate approach.
d) Calculate the BAC using the revised estimate approach.
e) Compare and discuss the results obtained in parts (c) and (d).

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 08:10
Which of the following is an easy way to remember the modified β€œx” tire rotation? a. nondrive wheels straight, cross the drive wheels b. drive wheels straight, cross the nondrive wheels c. drive wheels crossed, nondrive wheels straight d. drive wheels crossed, nondrive wheels crossed
Answers: 1
question
Engineering, 04.07.2019 18:10
An air compression refrigeration system is to have an air pressure of 100 psia in the brine tank and an allowable air temperature increase of 60Β°f for standard vapor compression cycle temperatures of 77 f entering the expansion cylinder and 14 f entering the compression cylinder, calculate the coefficient of performance a. 2.5 b 3.3 c. 4.0 d. 5.0
Answers: 3
question
Engineering, 04.07.2019 18:20
Most leaks in reciprocating air compressors can be detected and minimized by: (clo4) a)-detecting leakage areas using ultrasonic acoustic detector. b)-tightening joints and connections c)-replacing faulty equipment d)-all of the given options
Answers: 2
question
Engineering, 04.07.2019 18:20
Modern high speed trains do not have perpendicular expansion gaps where rails are joined end-to-end any more they are mostly welded together but what might happen if there was a spell of particularly hot weather that causes inspection of the tracks?
Answers: 1
You know the right answer?
An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a...
Questions
question
Mathematics, 25.07.2019 13:00
question
History, 25.07.2019 13:00
question
Computers and Technology, 25.07.2019 13:00
Questions on the website: 13722359