A 15 MW thermal power station has the following data: Cost of plant = $150 per kVA
Interest, taxes, insurance and depreciation rates = 25%
Cost of 11 kV-primary distribution system = $50000
Interest, taxes, insurance and depreciation rates = 10%
Annual fuel costs = $4Γ—105
Annual operation costs = $20000
Annual plant (fixed) maintenance costs = $10000
Annual plant (variable) maintenance costs = $15000
Maximum demand = 10 MW
Annual load factor = 50%
Power factor at generating power station terminals = 0.85 lagging
Determine the electrical supply tariff per unit at the consumers'
terminals, where:
- Plant reserve power is 10% over maximum generated power
demand.
- Efficiency of primary distribution system is 97%.
Find the percentage saving in electrical supply tariff served for the
consumers, if the load factor is raised to 75%.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The drive force for diffusion is 7 fick's first law can be used to solve the non-steady state diffusion. a)-true b)-false
Answers: 1
question
Engineering, 04.07.2019 18:10
You are making beer. the first step is filling the glass carboy with the liquid wort. the internal diameter of the carboy is 15 in., and you wish to fill it up to a depth of 2 ft. if your wort is drawn from the kettle using a siphon process that flows at 3 gpm, how long will it take to fill?
Answers: 1
question
Engineering, 04.07.2019 18:10
Condition monitoring is a major component of. (clo4) a)- predictive maintenance. b)-preventive maintenance c)-proactive maintenance d)-reactive maintenance.
Answers: 1
question
Engineering, 04.07.2019 18:20
Aheavily insulated piston-cylinder device contains 0.02 m3 of steam at 300 kpa and 200 Β°c. 1.2 mpa. d this process. team is now compressed in a reversible manner to a pressure of etermine the entropy change and the work done on the steam during this process
Answers: 1
You know the right answer?
A 15 MW thermal power station has the following data: Cost of plant = $150 per kVA
Interest,...
Questions
question
Mathematics, 11.02.2021 02:50
question
Mathematics, 11.02.2021 02:50
question
Health, 11.02.2021 02:50
Questions on the website: 13722363