Multiple Response: Which of the following are the most
commonly found issues with CPM scheduling, or the Critical
Path Method?
A) A CPM schedule is built before the overall cost of the project is determined and therefore projects are hurried near completion in order to stay under budget

B) An inaccurate prediction of the duration of project activities and tasks

C) A lack in ability to absorb delays

D) A failure to take into account the finite amount of resources available throughout the job

ansver
Answers: 2

Another question on Geography

question
Geography, 22.06.2019 07:20
Iam stuck on this question! 45 points : ) how do increases in temperature affect the density of ocean water? answer choices: (a) density does not change (b) density increases (c) density becomes variable (d) density decreases
Answers: 1
question
Geography, 22.06.2019 07:30
Why does less erosion & more deposition take place on the outside bank of a meander?
Answers: 1
question
Geography, 22.06.2019 15:00
Suggest two reasons why irrigation is important for human development of the desert
Answers: 1
question
Geography, 22.06.2019 15:10
Jessica finds out that the government introduced a new trade policy that will increase import tariffs. she calls for a meeting of all of the company'sdepartment heads to address this issue, since the new tariffs may increase the company's production costs. what is the purpose of this meeting? o a.operationsb.financec.strategic planningod.marketing
Answers: 1
You know the right answer?
Multiple Response: Which of the following are the most
commonly found issues with CPM schedulin...
Questions
question
French, 04.11.2021 20:00
question
Social Studies, 04.11.2021 20:00
Questions on the website: 13722367