There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks? select one: a. 0.26 b. 0.35 c. 0.58 d. 0.76

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Find the surface area of the prism formed by the net
Answers: 3
question
Mathematics, 21.06.2019 21:00
Glenda makes an online purchase for picture frames for $12.95 each and formats of $5.89 each the site says it taxes paid by the customer or 6.5% of the total purchase price shipping charges are based on the
Answers: 1
question
Mathematics, 21.06.2019 23:30
Drag each number to the correct location on the statements. not all numbers will be used. consider the sequence below. -34, -21, -8, 5, complete the recursively defined function to describe this sequence
Answers: 1
question
Mathematics, 21.06.2019 23:30
Arational number that is equivalent to -20/4?
Answers: 1
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2....