Asap! one construction company can do a certain job in ten days and a second construction company can do the same job in fifteen days. how many days will it take to complete the job if the two construction companies work together?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Astudent survey asked: "how tall are you (in inches)? " here's the data: 67, 72, 73, 60, 65, 86, 72, 69, 74 give the five number summary. a. median: 73, mean: 70.89, iqr: 5, min: 60, max: 74 b. 60, 66, 72, 73.5, 86 c. 60, 67, 72, 73, 74 d. 0, 60, 70, 89, 74, 100
Answers: 3
question
Mathematics, 21.06.2019 18:30
Write a polynomial function f of least degree that has rational coefficients, a leading coefficient of 1, and the given zeros. 3, 4+2i, 1+(sqrt)7 the answer is supposed to be: f(x)=x(^5)-13x(^4)+60x(^3)-82x(^2)-144x+360 what am i doing wrong?
Answers: 1
question
Mathematics, 22.06.2019 00:00
Afair die is cast four times. calculate the probability of obtaining exactly two 6's round to the nearest tenth of a percent
Answers: 1
question
Mathematics, 22.06.2019 00:20
Abag contains pieces of paper numbered from 5 to 9. a piece of paper is drawn at random. what is the theoretical probability of drawing a number less than 8?
Answers: 1
You know the right answer?
Asap! one construction company can do a certain job in ten days and a second construction company c...
Questions
question
English, 30.07.2021 09:00
question
English, 30.07.2021 09:00
question
Biology, 30.07.2021 09:00
Questions on the website: 13722361