If 6 workers complete a certain task in 12 days, how many workers are needed to finish the same task in 4 days?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
The measure of an angle is 117Β°. what is the measure of a supplementary angle?
Answers: 2
question
Mathematics, 22.06.2019 01:00
Ineed to know how to write question one in mathematical terms
Answers: 1
question
Mathematics, 22.06.2019 01:30
Urgent? will give brainliest given that the blue triangle is a right triangle, which expression correctly gives the area of the red square? a) a2 + b2 b) a2 - b2 c) a2 - c2 d) c2 - a2
Answers: 1
question
Mathematics, 22.06.2019 01:30
If 5x - 2 = -12, then x = a) -50 b) -4.4 c) -2.8 d) -2
Answers: 1
You know the right answer?
If 6 workers complete a certain task in 12 days, how many workers are needed to finish the same task...
Questions
question
English, 07.02.2021 20:30
question
Mathematics, 07.02.2021 20:30
question
English, 07.02.2021 20:30
Questions on the website: 13722361