you work as a librarian for a local community college. a
recent report on publishing project shows that show that
57.75% of the project has been completed in the past 7
work days. if work continues at the same rate,
approximately how many work days will be required in
total for the entire project?
your answer

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Jackie bought a bag of oranges. she used 3/8 of the oranges to make orange juice. she used 1/3 of the oranges to make a fruit salad. she put 1/8 of the oranges in a bowl on the table. she put 2/12 of the oranges in the refrigerator. a) jackie left more oranges on the table than she put in the refrigerator. b) jackie used fewer oranges to make orange juice than she left on the table. c) jackie put fewer oranges in the refrigerator than she used to make the fruit salad. eliminate d) jackie used more oranges to make a fruit salad than she used to make orange juice.
Answers: 1
question
Mathematics, 21.06.2019 15:00
(urgent ) use pi 3.14 to estimate the circumference of the circle to the nearest hundredth middle is 4in (urgent )
Answers: 1
question
Mathematics, 22.06.2019 00:00
Heather is a cashier. she can ring up 1212 customers in 99 minutes. at this rate, how many minutes does it take her to ring up 44 customers?
Answers: 1
question
Mathematics, 22.06.2019 00:40
Can you divide 25 into 4 equal groups? explain why or why not.
Answers: 1
You know the right answer?
10 poi
you work as a librarian for a local community college. a
recent report on publish...
Questions
question
Biology, 09.10.2019 07:30
question
Mathematics, 09.10.2019 07:30
question
Mathematics, 09.10.2019 07:30
question
English, 09.10.2019 07:30
question
Mathematics, 09.10.2019 07:30
question
English, 09.10.2019 07:30
Questions on the website: 13722367