Aproject can be completed by 5 workers in 24 days. how many workers are needed to finish the project in 15 days? the time
to complete a project is inversely proportional to number of people who are doing the project.
a 10
c6
b. 12
d. 8

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:10
Aphoto of a painting measured 13 x 17 inches the scale of the photo to the original painting is 1 inch to 3 inches. what is the size of this painting
Answers: 1
question
Mathematics, 21.06.2019 17:30
Asphere has a diameter of 10 in. what is the volume of the sphere?
Answers: 1
question
Mathematics, 21.06.2019 18:30
Over the last 8 nights, elyse earned the following in tips: {105, 120, 84, 95, 100, 132, 140}. if she earns $140 a night for the next four nights, which measure of center would increase more, the mean or median?
Answers: 3
question
Mathematics, 21.06.2019 18:30
15/16 as a decimal rounded to the nearest hundredth
Answers: 2
You know the right answer?
Aproject can be completed by 5 workers in 24 days. how many workers are needed to finish the project...
Questions
Questions on the website: 13722362