All the members of a construction crew work at the same pace. six of them working together are able to pour foundation in 22 hours.
a)how many hours would this job take if the number of workers decreased by factor of 2?
c)how many hours would this job take if the number of workers increased by factor of 4?
Answers: 3
Mathematics, 21.06.2019 14:40
In the diagram below, tan θ = sqrt 3. what is the value of m?
Answers: 3
Mathematics, 21.06.2019 17:30
Arecipe uses 2 cups of sugar to make 32 brownies. how many cups of sugar are needed to make 72 brownies?
Answers: 1
Mathematics, 21.06.2019 19:30
Awater holding tank measures 105 m long, 50 m wide, and 8 m deep. traces of mercury have been found in the tank, with a concen- tration of 60 mg/l. what is the total mass of mercury in the tank? answer in units of kg.
Answers: 1
Mathematics, 21.06.2019 21:00
Out of $20$ creepy-crawly creatures in a room, $80\%$ are flies and $20\%$ are spiders. if $s\%$ of the total legs belong to spiders, what is $s$?
Answers: 2
All the members of a construction crew work at the same pace. six of them working together are able...
Mathematics, 19.08.2019 16:30
Chemistry, 19.08.2019 16:30
Biology, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Biology, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Social Studies, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30
Mathematics, 19.08.2019 16:30