Mathematics, 17.09.2019 15:00 naomicervero

16 men are employed to do a work in 20 days. at the end of 12 days the work is only half done. how many additional number of men should be employed to complete the work in the stipulated time?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 22.06.2019 00:30
Which number can each term of the equation be multiplied by to eliminate the decimals before solving? 5.6j- 0.12=4+1.1j
Answers: 3
question
Mathematics, 22.06.2019 01:00
You went to a restaurant and spent $53.25 on the meal. there was a 6% sales tax. what was the amount of money, not including a tip, you spent at the restaurant?
Answers: 1
question
Mathematics, 22.06.2019 02:20
What are the solutions of the equation x4 – 5x2 – 14 = 0? use factoring to solve. someone !
Answers: 2
question
Mathematics, 22.06.2019 02:30
Cate purchases $1600 worth of stock and her broker estimates it will increase in value by 4.2% each year. after about how many years will the value of cate's stock be about $2000
Answers: 1
You know the right answer?
16 men are employed to do a work in 20 days. at the end of 12 days the work is only half done. how m...
Questions
question
Mathematics, 01.04.2021 23:30
question
Mathematics, 01.04.2021 23:30
Questions on the website: 13722359