An x-bar control chart was examined and no data points fell outside of the limits. can this process be considered in control?
a. not yet, there could be a pattern to the points.
b. not yet, the r-chart must be checked.
c. not yet, the number of samples must be known.
d. yes. both a and b

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
What are the relative frequencies to the nearest hundredth of the columns of the two-way table?
Answers: 2
question
Mathematics, 21.06.2019 19:00
Find the equation of a line whose slope is 2/5 and y- intercept is 2.write your answer in the form 1) ax+by+c=02) x/a+y/b=1
Answers: 1
question
Mathematics, 21.06.2019 19:30
When 142 is added to a number the result is 64 more times the number my options are 35 37 39 41
Answers: 1
question
Mathematics, 21.06.2019 21:10
Which exponential function has an initial value of 2? f(x) = 2(3x) f(x) = 3(2x)
Answers: 1
You know the right answer?
An x-bar control chart was examined and no data points fell outside of the limits. can this process...
Questions
question
Mathematics, 21.01.2021 22:20
question
Mathematics, 21.01.2021 22:20
question
Mathematics, 21.01.2021 22:20
Questions on the website: 13722360