Aproject has an expected completion time of 25 days. it is given that project completion time has a standard deviation of 2.645 days. what is the probability that this project will be completed less than 21 days and 12 hours?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:50
Which of the following points is collinear with (-2,1) and (0,3)
Answers: 3
question
Mathematics, 21.06.2019 19:10
The linear combination method is applied to a system of equations as shown. 4(.25x + .5y = 3.75) → x + 2y = 15 (4x – 8y = 12) → x – 2y = 3 2x = 18 what is the solution of the system of equations? (1,2) (3,9) (5,5) (9,3)
Answers: 1
question
Mathematics, 21.06.2019 22:00
Question 10 of 211 pointuse the elimination method to solve the system of equations. choose thecorrect ordered pair.10x +2y = 643x - 4y = -36a. (4,12)b. (-3, 11)c. (2,10)d. (-5, 8)
Answers: 1
question
Mathematics, 21.06.2019 23:00
Delbert keeps track of total of the total number of points he earns on homework assignments, each of which is worth 60 points. at the end of the semester he has 810 points. write an equation for delbert’s average homework score a in terms of the number of assignments n.
Answers: 3
You know the right answer?
Aproject has an expected completion time of 25 days. it is given that project completion time has a...
Questions
question
Mathematics, 17.04.2021 01:00
question
Mathematics, 17.04.2021 01:00
question
Mathematics, 17.04.2021 01:00
question
Mathematics, 17.04.2021 01:00
Questions on the website: 13722360