Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours. however, after working 8 hours, some of the workers left the group and the remaining workers could complete the job in 72 hours. how many workers left the team?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
The graph shows the distance y, in inches, a pendulum moves to the right (positive displacement) and to the left (negative displacement), for a given number of seconds x. how many seconds are required for the pendulum to move from its resting position and return? enter your answer in the box.
Answers: 2
question
Mathematics, 21.06.2019 16:20
An architect is designing a water fountain for a park she uses the given function to model the water jet flowing from the fountain nozzles where h(x) gives the height of the water jugs in feet x feet from the starting point h(x)=-1/20x+x+15
Answers: 2
question
Mathematics, 21.06.2019 18:00
Ammonia molecules have three hydrogen atoms and one nitrogen atom.how many of each atom arein five molecules of ammonia
Answers: 1
question
Mathematics, 21.06.2019 19:00
What is the equation of the line in point-slope form? y+ 4 = 1/2(x+4) y-4 = 1/2(x + 4) y-0 = 2(x - 4) y-4 = 2(8-0)
Answers: 2
You know the right answer?
Agroup of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours...
Questions
question
Spanish, 08.01.2021 08:40
question
Computers and Technology, 08.01.2021 08:40
question
History, 08.01.2021 08:40
question
History, 08.01.2021 08:40
Questions on the website: 13722359