Sara, kim, and john own a painting company. to paint a particular home, sara estimates it would take her 4 days. kim estimates 5.5 days. john estimates 6 days. how long would it take them to work together to paint the house.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Assume that a population of 50 individuals has the following numbers of genotypes for a gene with two alleles, b and b: bb = 30, bb = 10, and bb = 10. calculate the frequencies of the two alleles in the population’s gene pool.
Answers: 2
question
Mathematics, 21.06.2019 20:50
A. what is the area of the base? use complete sentences to explain your reasoning. b. what is the volume of the prism? use complete sentences to explain your reasoning.
Answers: 1
question
Mathematics, 21.06.2019 22:00
Liz is shipping a package to her friend. the maximum weight of a medium flat-rate box is 20 pounds, including the box which weighs 6 ounces. write and solve an inequality to describe the possible weight in pounds, w, of the contents that liz will ship to her friend if she must use a medium flat-rate box. use the drop-down menus to explain your answer.
Answers: 2
question
Mathematics, 21.06.2019 23:00
Edger needs 6 cookies and 2 brownies for every 4 plates how many cookies and brownies does he need for 10 plates
Answers: 1
You know the right answer?
Sara, kim, and john own a painting company. to paint a particular home, sara estimates it would take...
Questions
question
Mathematics, 14.01.2020 01:31
question
Social Studies, 14.01.2020 01:31
Questions on the website: 13722360