Acompany contracts to paint 3 houses. mr. brown can paint a house in 6 days while black would take 8 days and blue 12 days. after 8 days brown goes on vacation and black begins to work for a period of 6 days. how many days will it take blue to complete the contract?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Whose conclusion is correct? choose all that apply. (two max) elijah emily edward esme
Answers: 2
question
Mathematics, 21.06.2019 20:30
Aword processing program requires a 7- digit registration code made up of the digits 1,2,4,5,6,7 and 9 each number has to be used and no number can be used mor than once how many codes are possible
Answers: 1
question
Mathematics, 22.06.2019 02:20
Find the area of the surface obtained by rotating the curve z=4e^2y from y = 0 to y =1 about the y-axis. the area is square units
Answers: 2
question
Mathematics, 22.06.2019 02:30
Problem 3 a bank charges a service fee of $7.50 per month for a checking account. a bank account has $85.00. if no money is deposited or withdrawn except the service charge, how many months until the account balance is negative
Answers: 2
You know the right answer?
Acompany contracts to paint 3 houses. mr. brown can paint a house in 6 days while black would take 8...
Questions
question
Mathematics, 28.08.2019 20:10
question
Mathematics, 28.08.2019 20:10
Questions on the website: 13722363