Five workstations (1, 2, 3, 4, and 5) that produce about ten similar parts must be arranged into an in-line layout. The daily flow of parts between workstations is as follows: 40 parts from stations 5 to 2, 35 parts from stations 5 to 3, 20 parts from stations 3 to 1, 25 parts from stations 1 to 4, 60 parts from 3 to 2, 15 parts from stations 2 to 5, and 30 parts from stations 4 to 2.

A) Use the Hollier algorithm described to determine the most logical sequence of stations in the work system.
B) Draw the network diagram for the system.
C) Compute the percentage of in-sequence moves, by-passing moves, and backflow moves for the sequence.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
F(x)=|x| is shifted down 4 units and to the right 3 units.
Answers: 2
question
Mathematics, 21.06.2019 17:40
Bradley hikes 12 miles in 3 hours. in relation to bradley’s hike, which statement describes the expression
Answers: 2
question
Mathematics, 21.06.2019 18:00
Henry is an avid reader, he devours 90 pages in half an hour how many pages has henry read per minute?
Answers: 1
question
Mathematics, 21.06.2019 19:00
The distributive property allows you to say that 3(x − 1) = 3x −
Answers: 1
You know the right answer?
Five workstations (1, 2, 3, 4, and 5) that produce about ten similar parts must be arranged into an...
Questions
question
Health, 21.02.2020 05:05
question
Mathematics, 21.02.2020 05:05
question
Mathematics, 21.02.2020 05:06
Questions on the website: 13722359