Suppose a particular project has an expected completion time of 30 days; in other words, the critical path takes 30 days to finish. Further, the variance of the critical path is 25. Based on this information, please answer the following questions:

Find the probability that the project:
(1) Would be completed within 40 days
(2) Would take longer than 40 days to finish
(3) Would be completed within 20 days
(4) Would take longer than 20 days to finish

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Which expression is the factored from of 2/3x + 4?asap
Answers: 1
question
Mathematics, 21.06.2019 17:30
How many bananas are in a fruit bowl that has 200 total apples and bananas if there are 31 bananas for every 93 apples
Answers: 1
question
Mathematics, 21.06.2019 19:30
What is the result of adding the system of equations? 2x+y=4 3x-y=6
Answers: 2
question
Mathematics, 21.06.2019 20:00
Put the equation in slope intercept form by solving for y
Answers: 2
You know the right answer?
Suppose a particular project has an expected completion time of 30 days; in other words, the critica...
Questions
question
Mathematics, 29.10.2019 15:31
question
Mathematics, 29.10.2019 15:31
question
Mathematics, 29.10.2019 15:31
Questions on the website: 13722367