2. In a job shop, effective capacity is only 50 percent of design capacity, and actual output is 80 percent of effective output. What design capacity would be needed to achieve an actual output of eight jobs per week

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Using two or more complete sentences, describe how you can find a vector parallel to b=-2,3
Answers: 2
question
Mathematics, 21.06.2019 17:50
On a string instrument, the length of a string varies inversely as the frequency of its vibrations. an 11-inch string has a frequency of 400 cylces per second. find the frequency of a 10-icnch string.
Answers: 2
question
Mathematics, 21.06.2019 19:00
How do i start to solve? would appreciate a walk-thru! a bird sitting 16ft above the ground in an apple tree dislodges an apple. after how many seconds does the apple land on the ground? (assuming that no branches will interfere with it's fall)
Answers: 1
question
Mathematics, 21.06.2019 19:30
Order the measurements from the least to the greatest. 2,720 ml , 24.91 l , 0.0268 kl
Answers: 1
You know the right answer?
2. In a job shop, effective capacity is only 50 percent of design capacity, and actual output is 80...
Questions
question
French, 18.11.2020 17:50
Questions on the website: 13722359