The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
1. there are 25 students who started computer programming in elementary school and 25 students who started computer programming in middle school. the first group had a mean final project grade of 95% and the second group had a mean final project grade of 92%. the line plot shows the differences after 10 rerandomizations. determine whether the difference in the means of the two groups is significant based on the line plot. explain your answer.
Answers: 1
question
Mathematics, 21.06.2019 15:50
Fredrick designed an experiment in which he spun a spinner 20 times and recorded the results of each spin
Answers: 1
question
Mathematics, 21.06.2019 19:30
Find the distance between (0,5) & (-4,2)
Answers: 1
question
Mathematics, 21.06.2019 21:30
Plz hurry evaluate the expression a+b where a=8 and b=19
Answers: 1
You know the right answer?
The time required to complete a project is normally distributed with a mean of 80 weeks and a standa...
Questions
question
French, 08.12.2020 21:10
question
Computers and Technology, 08.12.2020 21:10
question
Mathematics, 08.12.2020 21:20
question
Mathematics, 08.12.2020 21:20
question
Mathematics, 08.12.2020 21:20
Questions on the website: 13722362