O determine how to crash activity times
a. normal activity costs and costs under maximum crashing must be known.
b. shortest times with crashing must be known.
c. realize that new paths may become critical.
d. All of the alternatives are true.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Gretchen is setting up for a banquet. she has 300 chairs and needs to distribute them evenly among t tables. how many chairs should she put at each table? write your answer as an expression.
Answers: 1
question
Mathematics, 21.06.2019 19:30
Richard save $32 in march he saved $48 in april and $38 in may then richard spent $113 on a keyboard how much money does richard have left
Answers: 1
question
Mathematics, 21.06.2019 20:10
60 2(x + 2) in the diagram, gef and hef are congruent. what is the value of x?
Answers: 2
question
Mathematics, 21.06.2019 20:50
An object is translated by (x + 4, y - 2). if one point in the image has the coordinates (5, -3), what would be the coordinates of its pre-image? (9, -5) (1, -5) (9, -1) (1, -1)
Answers: 1
You know the right answer?
O determine how to crash activity times
a. normal activity costs and costs under maximum crash...
Questions
question
Biology, 15.01.2020 16:31
question
Mathematics, 15.01.2020 16:31
question
Mathematics, 15.01.2020 16:31
question
Biology, 15.01.2020 16:31
Questions on the website: 13722360