You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
What is the y intercept of f(x)=(1/2)^x?
Answers: 1
question
Mathematics, 21.06.2019 20:30
Aregular pan has a length that is 4/3 the width. the total area of the pan is 432in.2. what is the width of the cake pan?
Answers: 1
question
Mathematics, 21.06.2019 23:30
On this question. a hypothermia occurs when a person's body temperature drops below 95 degrees fahrenheit. write and solve an inequality that describes how much lower the body temperature of a person with hypothermia will be than the body temperature of a person with a normal temperature of 98.6 degrees fahrenheit
Answers: 1
question
Mathematics, 22.06.2019 00:30
On the way home from visiting his family, vincent’s plane cruised at an altitude of 3.2 × 10^4 feet. he had heard that a man named felix baumgartner skydived from an altitude of 1.28 × 10^5 feet. vincent wants to know how much higher felix went on his skydiving trip. question 1 you have already seen how adding numbers works in either scientific notation or standard notation. but can you subtract numbers in scientific notation and get the same results as subtracting in standard notation? to find out, first solve vincent’s problem in standard notation. part a write the cruising altitude of vincent’s plane in standard notation.
Answers: 2
You know the right answer?
You have just used the network planning model and found the critical path length is 30 days and the...
Questions
question
Mathematics, 06.01.2021 20:40
question
Mathematics, 06.01.2021 20:40
question
Mathematics, 06.01.2021 20:40
question
Mathematics, 06.01.2021 20:40
question
Mathematics, 06.01.2021 20:40
Questions on the website: 13722363