A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how long do they need to finish the job?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
Evaluate the discriminant of each equation. tell how many solutions each equation has and whether the solutions are real or imaginary. x^2 - 4x - 5 = 0
Answers: 2
question
Mathematics, 21.06.2019 20:10
A. use the formula for continuous compounding with the original example: $1000 invested at 2% for 1 year. record the amount to 5 decimal places. use a calculator. b. compare it to the result using the original compound interest formula with n = 365 calculated to 5 decimal places. which has a larger value? explain.
Answers: 1
question
Mathematics, 21.06.2019 21:30
This is a map of the mars exploration rover opportunity predicted landing site on mars. the scale is 1cm : 9.4km. what are the approximate measures of the actual length and width of the ellipse? i mostly need to know how to set it up : )
Answers: 3
question
Mathematics, 22.06.2019 00:00
How many liters of peroxide should be added to 12 liters of an 8% peroxide solution so that the resulting solution contains 16% peroxide?   original added new amount of peroxide 0.96 liters x 0.96 + x amount of solution 12 liters x 12 + x 0.18 liter 1.14 liters 1.92 liters 2.10 liters
Answers: 1
You know the right answer?
A person can do a job in 6 days. Another can do the same job in 4 days. If they work together, how l...
Questions
question
Arts, 11.10.2020 20:01
question
Mathematics, 11.10.2020 20:01
question
Mathematics, 11.10.2020 20:01
question
Mathematics, 11.10.2020 20:01
question
Spanish, 11.10.2020 20:01
question
English, 11.10.2020 20:01
question
Mathematics, 11.10.2020 20:01
question
Mathematics, 11.10.2020 20:01
Questions on the website: 13722359