Two companies working together can clear a parcel of land in 24 hours. Working alone, it would take Company A 10 hours longer to clear the land than it would Company B. How long would it take Company B to clear the parcel of land alone

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:40
Aregular hexagon has sides of 2 feet. what is the area of the hexagon? 12 ft2 12 ft2 24 ft2 6 ft2
Answers: 2
question
Mathematics, 21.06.2019 18:30
Over the last 8 nights, elyse earned the following in tips: {105, 120, 84, 95, 100, 132, 140}. if she earns $140 a night for the next four nights, which measure of center would increase more, the mean or median?
Answers: 3
question
Mathematics, 21.06.2019 20:00
Which part of a 2-column proof is the hypothesis of the conjecture? a) given b) reasons c) prove d) statements ! i think it's b but i'm not quite
Answers: 3
question
Mathematics, 21.06.2019 22:50
Use the quadratic function to predict f(x) if x equals 8. f(x) = 25x2 − 28x + 585
Answers: 1
You know the right answer?
Two companies working together can clear a parcel of land in 24 hours. Working alone, it would take...
Questions
question
Mathematics, 27.06.2019 06:30
question
Mathematics, 27.06.2019 06:30
question
Mathematics, 27.06.2019 06:30
Questions on the website: 13722363