A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
The owner of the plant nursery where you were tells you to fill 350 ml bottles from a 30 l from a fertilizer
Answers: 1
question
Mathematics, 22.06.2019 04:00
What is being done to the variable in the equation 3 + g = -9? the number 3 is being added to it. the number 3 is being subtracted from it. the number -9 is being added to it. the number -9 is being subtracted from it.
Answers: 2
question
Mathematics, 22.06.2019 04:00
Mrs. chibas is making chocolate chip cookies for her daughter's class. she bought a tub of chocolate chip cookie dough that contained 57.6 ounces of dough. if each cookie needs 1.2 ounces of dough, how many cookies can she make
Answers: 1
question
Mathematics, 22.06.2019 05:00
He factorization of 8x3 – 125 is (2x – 5)(jx2 + kx + 25). what are the values of j and k?
Answers: 1
You know the right answer?
A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance...
Questions
question
Business, 12.05.2021 22:00
question
Mathematics, 12.05.2021 22:00
question
Mathematics, 12.05.2021 22:00
question
Mathematics, 12.05.2021 22:00
question
Chemistry, 12.05.2021 22:00
Questions on the website: 13722363