An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

A) About 8 days

B) About 9 days

C) About 10 days

D) About 11 days

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
What were mkh company's cash flows from (for) operating activities in 20x1? $(180,300) $233,100 $268,200 $279,400?
Answers: 2
question
Mathematics, 21.06.2019 19:30
Which table shows a proportional relationship between miles traveled and gas used?
Answers: 2
question
Mathematics, 21.06.2019 21:00
In the figure below, triangle rpq is similar to triangle rts. what is the distance between p and q? a. 24 b. 42 c.50 d. 54
Answers: 1
question
Mathematics, 21.06.2019 23:00
Apackage of orgainc strwberries costs $1.50 while there in season and $2.25 when not in season what the percent increase
Answers: 1
You know the right answer?
An activity has a pessimistic time that is four times as long as its most likely time and six times...
Questions
question
Mathematics, 11.05.2021 18:00
question
Physics, 11.05.2021 18:00
Questions on the website: 13722361