C(x) = 81,000 + 110x + 6x3/2
Find the production level that will minimize the average cost.
What is the minimum average cost?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 21:30
Every weekday, mr. jones bikes from his home to his job. sometimes he rides along two roads, the long route that is shown by the solid lines. other times, he takes the shortcut shown by the dashed line. how many fewer kilometers does mr. jones bike when he takes the shortcut instead of the long route?
Answers: 1
question
Mathematics, 21.06.2019 21:30
An internet company charges $8.95 per month for the first 3 months that it hosts your web site. then the company charges $11.95 per month for web hosting. how much money, in dollars, will the company charge for 8 months of web hosting?
Answers: 1
question
Mathematics, 22.06.2019 01:00
If log_3(x)=4.5 and log_3(y)=3, what is log_3(x^2/y)? a. 3b. 6.75c. 6d. 1.5
Answers: 2
question
Mathematics, 22.06.2019 04:00
Ineed with 8,9 and 10 love ya guysss
Answers: 1
You know the right answer?
C(x) = 81,000 + 110x + 6x3/2
Find the production level that will minimize the average cost.
Questions
question
Social Studies, 09.10.2019 09:20
question
History, 09.10.2019 09:20
question
Mathematics, 09.10.2019 09:20
Questions on the website: 13722360