It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:30
What is the slope of the line shown below?
Answers: 1
question
Mathematics, 21.06.2019 21:30
Consider circle c with angle acb measuring 3/4 radians.if minor arc ab measures 9 inches, what is the length of the radius of circle c? if necessary, round your answer to the nearest inch.
Answers: 2
question
Mathematics, 21.06.2019 22:30
Which of the following is an example of a rational number? a. π b. √ 9 c. √ 8 d. 3.8362319
Answers: 1
question
Mathematics, 21.06.2019 22:40
Ntriangle abc, m∠a = 35° and m∠b = 40°, and a=9. which equation should you solve to find b?
Answers: 2
You know the right answer?
It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electrici...
Questions
question
Mathematics, 23.03.2020 17:26
question
Mathematics, 23.03.2020 17:26
Questions on the website: 13722362