Mathematics, 01.07.2020 15:01 Alexandra001
Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's earliest finish is 18: while C's is 20. F's late start is 26. Which of the following is definitely true?
a. D is critical and has zero slack.
b. B is a critical activity.
c. F is critical and has zero slack.
d. D has no slack but is not critical.
e. C is completed before B.
Answers: 2
Mathematics, 21.06.2019 14:30
Ahigh definition tv cost $800 with a down payment of 2/5 of the cost. how much is left to pay, in dollars after the down payment has been made?
Answers: 1
Mathematics, 21.06.2019 17:00
The sum of the reciprocal of a positive number and the reciprocal of 2 more than the number is 3/4 equation: the number is
Answers: 2
Mathematics, 21.06.2019 19:00
Rena is building a 1: 180 scale model of a real castle. her model has a rectangular base that is 3 feet wide and 4 feet long what is the area of the base of the actual castle in square feet
Answers: 2
Mathematics, 21.06.2019 21:30
Atrain leaves little? rock, arkansas, and travels north at 90 kilometers per hour. another train leaves at the same time and travels south at 80 kilometers per hour. how long will it take before they are 680 kilometers? apart?
Answers: 1
Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's ear...
Biology, 09.10.2021 03:20
Mathematics, 09.10.2021 03:20
Law, 09.10.2021 03:20
Mathematics, 09.10.2021 03:20
Computers and Technology, 09.10.2021 03:20
Mathematics, 09.10.2021 03:30
Biology, 09.10.2021 03:30
Mathematics, 09.10.2021 03:30
Mathematics, 09.10.2021 03:30