subject
Mathematics, 08.07.2020 23:01 angelashaw449

(i) You are the cost Engineer for a construction company in charge of building a new bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:10
Next, chad created this graph with ordered pairs that show the possible ratios of the number of damage to defense cards in his deck.what error chad make?
Answers: 1
question
Mathematics, 21.06.2019 15:30
Franco wants to double the volume of the cone. what should he do?
Answers: 2
question
Mathematics, 21.06.2019 18:30
The final cost of a sale is determined by multiplying the price on the tag by 75%. which best describes the function that represents the situation?
Answers: 1
question
Mathematics, 21.06.2019 23:30
Solve for x and select the correct answer
Answers: 3
You know the right answer?
(i) You are the cost Engineer for a construction company in charge of building a new bridge. The co...
Questions
question
Computers and Technology, 30.07.2020 14:01
question
Mathematics, 30.07.2020 14:01
question
Arts, 30.07.2020 14:01
Questions on the website: 13722361