if 28 men can complete a work in 16 days wiil 8 men take to complete that work is it a.14 b.48 c.56 d.128

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:40
The graph below could be the graph of which exponential function?
Answers: 2
question
Mathematics, 21.06.2019 16:30
An airport in death valley is 60 feet below sea level, and an airplane is flying 2,000 feet above sea level. how many feet must the plane descend in order to land? a. 2060 b. 2000 feet c. 1940 feet d. 1880 feet e.1400 feet will mark as brainliest
Answers: 2
question
Mathematics, 21.06.2019 16:50
Kapil needed to buy a long wooden beam. he went to two sawmills that each charge an initial fee plus an additional fee for each meter of wood. the following equation gives the price (in dollars) of a wooden beam from the first sawmill as a function of its length (in meters). p = 5+20xp=5+20x
Answers: 1
question
Mathematics, 21.06.2019 18:00
How many triangles can be drawn with side lengths 4 centimeters, 4.5 centimeters, and 9 centimeters? explain
Answers: 1
You know the right answer?
if 28 men can complete a work in 16 days wiil 8 men take to complete that work is it a.14 b.48 c.56...
Questions
Questions on the website: 13722361