5. A can do a piece of work in 8 days which B alone can do in 10 days. In how many days both working
together can do it?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
What is this equation in point-slope form?
Answers: 1
question
Mathematics, 21.06.2019 15:00
If 1 is divided by the sum of y& 4. the result is equal to 3 divided by 4 .find the value of m?
Answers: 1
question
Mathematics, 21.06.2019 15:00
With these: 18/36 = 1/? missing number change 1 5/8 to improper fraction. change 19/5 to a mixed number.
Answers: 1
question
Mathematics, 21.06.2019 18:00
Describe the relationship between the angles of similar triangles and the sides of similar triangles
Answers: 1
You know the right answer?
5. A can do a piece of work in 8 days which B alone can do in 10 days. In how many days both workin...
Questions
question
English, 31.10.2019 00:31
question
Mathematics, 31.10.2019 00:31
question
Mathematics, 31.10.2019 00:31
Questions on the website: 13722361