The time required to complete a job varies inversely as the number of
people working. It took 22 painters 494 hours to paint a wall. How long
would it have taken 19 people to have done the job?
Answers: 2
Mathematics, 21.06.2019 13:30
The equation y=mx+b is the slope-intercept form of the equation of a line. what is the equation solved for b? y-m=b y-mx=b y/mx=b y/m-x=b
Answers: 2
Mathematics, 21.06.2019 16:00
Pick the expression that matches this description: a polynomial of the 5th degree with a leading coefficient of 7 and a constant term of 6 (choice a) 7x^5+2x^2+6 (choice b) 7x^6−6x^4+5 (choice c) 6x^7−x^5+5 (choice d) 6x^5+x^4+7
Answers: 2
Mathematics, 21.06.2019 21:30
Find the volume of the solid obtained by rotating the region enclosed by the curves y=1x and y=7^-x about the x-axis. (use symbolic notation and fractions where needed.) volume =
Answers: 3
The time required to complete a job varies inversely as the number of
people working. It took 22 pa...
Mathematics, 03.02.2020 12:58
Mathematics, 03.02.2020 12:58
Business, 03.02.2020 12:58
Geography, 03.02.2020 12:58
Biology, 03.02.2020 12:58
Mathematics, 03.02.2020 12:58
Mathematics, 03.02.2020 12:58
Mathematics, 03.02.2020 12:58
Mathematics, 03.02.2020 12:58
Social Studies, 03.02.2020 12:58