2) If 20 workers can build a house in 45 days, how many more workers are needed to complete it in 30 days?
А
6
B
15
С
10
D
18


2) If 20 workers can build a house in 45 days, how many more workers are needed

to complete it in

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Given f(x)=2x^2-8x+6 and g(x)=3x-1 find f(x) +g(x) a. 2x^2+5x+5 b.2x^2-11x+7 c. 2x^2-5x+5 d.2x^2-5x-5
Answers: 1
question
Mathematics, 22.06.2019 02:10
Which diagram best shows how fraction bars can be used to evaluate 1/2 divided by 1/4?
Answers: 2
question
Mathematics, 22.06.2019 03:00
Ashley spent half of her lunch money on a turkey sandwich. then she spent two-thirds of the money she had left on a bottle of juice and the rest of the money on a cookie. if the cookie cost $.75, how much lunch money did ashley have to start with?
Answers: 2
question
Mathematics, 22.06.2019 03:20
What is the definition of a surd.give an example.
Answers: 1
You know the right answer?
2) If 20 workers can build a house in 45 days, how many more workers are needed to complete it in 3...
Questions
question
Mathematics, 21.08.2020 18:01
question
Mathematics, 21.08.2020 18:01
question
English, 21.08.2020 18:01
question
Geography, 21.08.2020 18:01
Questions on the website: 13722361