Mathematics, 04.12.2020 02:40 missalawode28

Photon Technologies, Inc., a manufacturer of batteries for mobile phones, signed a contract with a large electronics manufacturer to produce three models of lithium-ion battery packs for a new line of phones. The contract calls for the following: Battery Pack Production Quantity
PT-100 200,000
PT-200 100,000
PT-300 150,000
Photon Technologies can manufacture the battery packs at manufacturing plants located in the Philippines and Mexico. The unit cost of the battery packs differs at the two plants because of differences in production equipment and wage rates. The unit costs for each battery pack at each manufacturing plant are as follows:

Plant
Product Philippines Mexico
PT-100 $0.95 $0.98
PT-200 $0.98 $1.06
PT-300 $1.34 $1.15
The PT-100 and PT-200 battery packs are produced using similar production equipment available at both plants. However, each plant has a limited capacity for the total number of PT-100 and PT-200 battery packs produced. The combined PT-100 and PT-200 production capacities are 175,000 units at the Philippines plant and 160,000 units at the Mexico plant. The PT-300 production capacities are 75,000 units at the Philippines plant and 100,000 units at the Mexico plant. The cost of shipping from the Philippines plant is $0.18 per unit, and the cost of shipping from the Mexico plant is $0.10 per unit.

(a) Develop a linear program that Photon Technologies can use to determine how many units of each battery pack to produce at each plant to minimize the total production and shipping cost associated with the new contract. If the constraint is one, enter "1". If the amount is zero, enter "0".
Let P1 = number of PT-100 battery packs produced at the Philippines plant
P2 = number of PT-200 battery packs produced at the Philippines plant
P3 = number of PT-300 battery packs produced at the Philippines plant
M1 = number of PT-100 battery packs produced at the Mexico plant
M2 = number of PT-200 battery packs produced at the Mexico plant
M3 = number of PT-300 battery packs produced at the Mexico plant

Min
P1 +
P2 +
P3 +
M1 +
M2 +
M3
s. t.
P1 +
P2 +
P3 +
M1 +
M2 +
M3 =
Production PT-100
P1 +
P2 +
P3 +
M1 +
M2 +
M3 =
Production PT-200
P1 +
P2 +
P3 +
M1 +
M2 +
M3 =
Production PT-300
P1 +
P2 +
P3 +
M1 +
M2 +
M3 ≀
Capacity Phi PT-100 & 200
P1 +
P2 +
P3 +
M1 +
M2 +
M3 ≀
Capacity Mex PT-100 & 200
P1 +
P2 +
P3 +
M1 +
M2 +
M3 ≀
Capacity Phi PT-300
P1 +
P2 +
P3 +
M1 +
M2 +
M3 ≀
Capacity Mex PT-300
P1, P2, P3, M1, M2, M3 β‰₯ 0
(b) Solve the linear program developed in part (a), to determine the optimal production plan. If the amount is zero, enter "0".
Qty Produced
Phillipines Mexico
PT-100
PT-200
PT-300
Total Cost = $
(c) Use sensitivity analysis to determine how much the production and/or shipping cost per unit would have to change to produce additional units of the PT-100 in the Philippines plant.
If required, round your answer to two decimal digits.
At least $ / unit.
(d) Use sensitivity analysis to determine how much the production and/or shipping cost per unit would have to change to produce additional units of the PT-200 in the Mexico plant.
If required, round your answer to two decimal digits.
At least $ / unit.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
The label on the car's antifreeze container claims to protect the car between ? 40Β°c and 125Β°c. to convert celsius temperature to fahrenheit temperature, the formula is c = 5 over 9 (f ? 32). write and solve the inequality to determine the fahrenheit temperature range at which this antifreeze protects the car. ? 40 > 5 over 9 (f ? 32) > 125; ? 40 > f > 257 ? 40 < 5 over 9 (f ? 32) < 125; ? 40 < f < 257 ? 40 < 5 over 9 (f ? 32); ? 40 < f 5 over 9 (f ? 32) < 125; f < 257
Answers: 2
question
Mathematics, 21.06.2019 20:20
20 solve 2(4 x + 3) < 5 x + 21. a) { x | x < 9} b) { x | x > -5} c) { x | x > -9} d) { x | x < 5}
Answers: 2
question
Mathematics, 21.06.2019 22:00
What value is a discontinuity of x squared plus 8 x plus 4, all over x squared minus x minus 6?
Answers: 2
question
Mathematics, 22.06.2019 00:20
What is the slope of the line passing through the points (3, 3) and (5, 7) ? 1. 2 2. 1/2 3. βˆ’2 4. βˆ’1/2
Answers: 2
You know the right answer?
Photon Technologies, Inc., a manufacturer of batteries for mobile phones, signed a contract with a l...
Questions
question
English, 29.09.2020 14:01
question
Mathematics, 29.09.2020 14:01
question
Mathematics, 29.09.2020 14:01
question
History, 29.09.2020 14:01
question
Physics, 29.09.2020 14:01
question
Biology, 29.09.2020 14:01
question
Mathematics, 29.09.2020 14:01
Questions on the website: 13722360