A and B can do a piece of work in 18 days , B and C in 24 days and A and C in 36 days . How much time will A alone take to finish the work?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Find a number such that if you add 8 and divide the result by 4 you will get the same answer as if you subtracted 3 from the original number and divided by 2
Answers: 3
question
Mathematics, 21.06.2019 18:30
Water flows at a steady rate from a tap. its takes 40 seconds to fill a 4 litre watering can from the tap. the rate at which water flows from the tap is halved. complete: 4 litres into cm3
Answers: 3
question
Mathematics, 21.06.2019 18:30
Identify the polynomial. a2b - cd3 a.monomial b.binomial c.trinomial d.four-term polynomial e.five-term polynomial
Answers: 1
question
Mathematics, 21.06.2019 19:00
Moira has a canvas that is 8 inches by 10 inches. she wants to paint a line diagonally from the top left corner to the bottom right corner. approximately how long will the diagonal line be?
Answers: 1
You know the right answer?
A and B can do a piece of work in 18 days , B and C in 24 days and A and C in 36 days . How much tim...
Questions
question
Social Studies, 02.02.2021 23:00
question
Mathematics, 02.02.2021 23:00
question
English, 02.02.2021 23:00
question
Chemistry, 02.02.2021 23:00
question
Mathematics, 02.02.2021 23:00
Questions on the website: 13722361